Ballymacarney Rd.

Precision at strip stage created certainty for 
the rest of the project.

Client

RJB Civils

Location

Co. Dublin

Scope

Vegetation clearance & controlled topsoil stripping

Project Type

Infrastructure enabling works

Challenge

Restricted access, overhead power lines, urban interface

Outcome

Early handover enabling the next 
phase of construction

Enabling Works
Earthworks

Ballymacarney Road formed a critical early phase of a wider infrastructure programme, requiring enabling works and site preparation ahead of roads and drainage construction.

ROQ was appointed to deliver vegetation clearance, topsoil stripping and associated site preparation works, establishing the conditions for efficient progression into the next phase of development.

While often viewed as preliminary works, early-stage site preparation can have a significant impact on programme, cost and downstream delivery. ROQ’s approach focused on disciplined planning, controlled execution and protection of design levels from the outset, reducing avoidable risk and supporting predictable project progression.

The challenge

Although the scope appeared straightforward, several factors introduced operational risk:

  • Restricted site access
  • Overhead power lines limiting plant movements
  • An urban interface requiring careful management 
of public interaction
  • A limited weather window for safe stripping operations

 

In addition, the condition of the underlying formation meant that aggressive stripping risked disturbing design levels and creating unnecessary remediation work later in the program.

Early-stage decisions therefore had the potential to impact program certainty and downstream costs.

Machinery working on Ballymacarney Road
Digger stripping top soil

The solution

ROQ approached the works as a controlled operation 
rather than a bulk earthworks exercise.

Vegetation was first removed and stockpiled locally to enable reuse on site. A tightly controlled topsoil strip was then undertaken using GPS-guided plant, allowing the team to remove material accurately while protecting the underlying formation layer.

Additional measures included:

  • Safety infrastructure installed to manage operations under overhead power lines
  • Site security controls implemented to manage interaction with neighbouring residents
  • Deployment of sufficient plant capacity during a suitable weather window to accelerate works safely

 

Working to a precise and shallow cut allowed stripping operations to progress efficiently while maintaining strict control over ground conditions.

The result

At strip stage, accuracy matters more than speed. Well controlled early works can quietly remove risk from the rest 
of a construction program.

By prioritising precision over speed, the project delivered several key advantages:

  • Reduced material disposal requirements
  • Avoided re-import of construction material
  • Protection of formation levels across the site
  • Greater certainty for follow-on roads and drainage works

 

The site was handed over significantly earlier than anticipated, enabling the next phase of development to begin ahead of program.

This project demonstrates ROQ’s ability to deliver precise enabling works in constrained environments while protecting program certainty for clients and project partners.

Projects

Four disciplined phases. Decisions grounded in experience, not assumptions.

Projects

Explore some of our projects and see how we’re transforming the built world.
Latest Projects

Construction

From preconstruction to virtual design and construction, we offer a wide range of services to meet your building needs.

Lump-Sum Contracting

The Construction Manager is not required to provide an estimate or contract cost breakdown and does not typically participate in pre-construction.

Design - Build

Certainty of outcome. It’s why our clients choose us for their most challenging Design/Build projects.

Pre-Construction Services

From engineering to preconstruction, we offer a variety of services and delivery methods.